Vejen Railway Station

Client: Net Denmark
Type of Contract: Main contract
Contract sum: kr. 20.0 million.
Construction period: 2009
Engineer: Ramboll A / S

Info

Overview

As part of the Danish Rail way renewal projects a 3 km long track on “Vejen” Station was rebuilt and a new platform incl. edges and coating was built. The work was carried out over a very short period of intense and concentrated work with track closures.

Key figures
  • 3,000 m³ gravel ballast
  • 1,500 m drains
  • 55 pcs.. wells
  • 10,000 m³ soil work
  • 1,600 m² platform works

Back to Railway