Sewer, Lilletoften, Ballerup

Client: Supply Ballerup Service A/S
Type of Contract: Main contract
Contract sum: kr. 3,5 mio.
Construction period: 2012-2013
Engineer: Rambøll A/S

Info

Overview

The pipelines around the junction between the streets “Lilletofte / Ballerup Boulevard / Harrestruproad was put through a thorough inspection. Clearing of the detected errors and deficiencies in the lines were done by excavation, since the drain along the route were largely “oval” and rerounding could not be done by CIPP Lining.

Key figures
  • 440 m rainwater pipes
  • 8 stk. wells
  • 1.000 m² Bottom protection
  • 1.000 m² Base course work
  • 230 ton asphalt work