Ringsted-Femern

Client: Banedanmark
Type of Contract: Turnkey
Contract sum: DKK 150 mio.
Construction period: 2017-2022
Engineer: MOE A/S & Jens Ostenfeld

Info

Oversigt

Establishment of modernised train stations
The Ringsted-Femern Railway is Banedanmarks upgrade of the existing track between Ringsted and Nykøbing Falster.

Barslund signed a contract that includes six stations which are Glumsø, Lundby, Vordingborg, Nr. Alslev, Eskildstrup and Nykøbing Falster.

The turnkey contract included detailed design, new platforms and forecourt, the creation of walkways with elevators, demolition, road work, station areas with sewerage and station areas.

Futhermore pipelines for power cables, signal cables and lighting were installed, noise screens and platform fronts was established.

At five stations, new walkways and elevator pits were constructed and in this connection, retaining walls and pile framing were carried out.

A large part of the work was carried out with tracks in operation, Barslund therefore had extra focus on QHSE during both planning and execution.

Hovedmængder

● 4.000 m³ earthwork
● 1.000 m³ gravelwork
● 500 tons asphaltwork
● 100 m² sheetpiling
● 155 m sound barrier
● pilework