Østbanen

Client: Entreprise
Type of Contract: Main contract
Contract sum: kr. 5.5 million.
Construction period: 2009
Engineer: Atkins

Info

Overview

The main purpose of the contract was to upgrade the line speed at Østbanen from 75 km / h to 100 km / h.
The project included:
• Track Alignment
• Renovation of passes
• Renovation of the track box in unused level crossing
• Dam extensions
• Rebuilding of Faxe South station
• Establishment of 2 buffer stops

Key figures
  • 5,500 m³ soil work
  • 4,500 m² base gravel work
  • 4,500 m² sub base work
  • 3,500 m³ crushed stone laying
  • 4,000 m² asphalting