Main pipes, H.C. Andersens vej

Client: Supply Helsingor A / S
Type of Contract: Main contract
Contract sum: kr. 5.0 million.
Construction period: 2011-2012
Engineer: COWI A / S

Info

Overview

The work included replacement of existing sewer lines. The construction contract was carried out so that the rainwater could be separated and therefore no longer be a burden on the joint cord through Helsingør. The work was done in residential neighborhoods, which placed great demands on logistics and citizen management.

Key figures
  • 150 m concrete pipes Ø1000mm
  • 500 m plastic wires
  • 10 pcs. concrete wells
  • 300 meters rainwater pipes
  • 1,800 m³ bottom protection work
  • 1,800 m² base gravel work
  • 1,800 m² gravel asphalt concrete and mastic asphalt