Post Nord – Logistic stock and transport terminal

Client: DS Flexhal A/S
Type of Contract: Trade-by-trade Contract
Contract sum: DDK 12,6 mio.
Construction period: 2016-2017
Engineer: None

Info

Overview

Post Nord has built a new logistics warehouse and a new transport terminal in Køge.

Barslund has carried out terrain regulation, bearing construction, coating, drainage and sewage work in relation to the logistics warehouse.

In relation to the transport terminal Barslund has carried out terrain regulation, bearing construction, coating, drainage and sewage work. In order for the coating to hold the many heavy trucks that on a daily basis run through the terminal, the 50,000 m² concrete coating was carried out in high quality, in high strength cement-stabilized foundation.

Key figures

● 74.289 m³ soil work
● 75.465 m³ calcium stabilization
● 34.790 m³ incorporation of bottom gravel
● 55.152 m² cement stabilization
● 16.577 m³ base gravel work
● 89.214 m³ subbase work
● 58,000 m³ concrete coating
● 25,296 m³ stable gravel work
● 8,030 m wire work