Hammar Traffic Square

Client: Trafikverket
Type of contract: Turnkey
Contract sum: 16.1 mio. SEK
Construction period: 2017

Info

Oversigt

Rebuilding of Hammar Traffic Square

The contract is for the rebuilding of Hammar Traffic Square in Kristianstad on route 118 and the extension of the exit ramp along the E22, which will lead to a new commercial area at Hammarslund. The object is a total contract and it is included to perform two circulation sites.

Hovedmængder

● 13.000 m² asphalt removal
● 5.000 m³ excavation
● 5.000 m² geotextile
● 18.500 m² support layer
● 3.500 m³ subbase
● 2.000 m curbs
● 18.000 m² asphalt
● 1.000 m² plant bed

Back to references