Bispebjerg ­Hospital, Site Development

Client: Capitol Region
Type of Contract: Main contract
Contract sum: 23 mio. DKK
Construction period: 2019-2020
Engineer: PLH Arkitekter

Info

Development for new hospital wing
The contract deals with building development in connection with the expansion of Bispebjerg Hospital’s new psychiatric ward – New Psychiatry Bispebjerg and includes clearing, cancellation of existing pipes, excavation of construction pits, establishment of surface drainage, including two large pump wells, controlled sub-drilling and groundwater lowering.

The work includes the establishment of two Ø3000 pump wells at a depth of 6-9 meters, as well as the excavation of existing Ø400 pipes at a depth of 4 meters.

In addition, access roads for emergency vehicles from Tuborgvej and into the hospital must be maintained throughout the contract.

Back to references