Better Bus Nørre Camp

Client: City of Copenhagen
Type of Contract: Main contract
Contract sum: kr. 68.0 million.
Construction period: 2013-2014
Engineer: Viatrafik A / S

Info

Overview

The contract includes the establishment of a high-class bus solution on the route from Hans Knudsen’s Square in the north to Ny Nørreport Station in the south of Copenhagen. the contract incl. work on the adjoining roads and especially at the intersections on the project route. On the rest of the project route and especially at traffic lights along the way, other traffic measures has been established, upgrading the buses that run on that route. The work is done in highly trafficked areas with different types of road users to regard.

Key figures
  • 14,000 tons demolition
  • 23,000 tons excavation work
  • 1,800 m³ topsoil work
  • 1,100 m drains
  • 3,400 m rainwater pipes
  • 4,500 m³ bottom protection work
  • 4,600 m³ base gravel work
  • 60,300 m² asphalting
  • 22,500 m curbs
  • 14,200 m road striping